The Operational Report was presented by T J Riggio. He updated the Board on plans
Presented in: Board of Directors Regular Meeting - September 17, 2025 on 2025-09-17
Staff Report & Agenda Item Details
The Operational Report was presented by T J Riggio. He updated the Board on plans for rehab at Lift Station No. 11 in DCBE to get the lift station to an operable state. The electrical upgrades will be a part of the eventual project rebuild. eHT will be designing the electrical upgrades required ( cost unknown at this time). AMUD crews will repair the plumbing and structural in the current wet well; the cost is anticipated to be $30K. The plumbing and structural work will not carry over to the new rebuilt lift station but is needed at this time in order to have an operable lift station. Currently working on getting quotes.