F • REGULARActon Municipal Utility District (Hood County)

The Engineer's Report was presented by Chris Hay, P.E. ofEnprotec/Hibbs & Todd

Presented in: Board of Directors Regular Meeting - February 18, 2026 on 2026-02-18
Meeting Agenda PDF

Staff Report & Agenda Item Details

The Engineer's Report was presented by Chris Hay, P.E. ofEnprotec/Hibbs & Todd ( eHT). He reported on the following: • WWTP #2 Improvements - The current substantial and final completion dates are June 5, 2025 and July 10, 2025 respectively based on the approval of Change Order 2. BAR is working to wrap up final site work and is working towards final completion. • Pecan Plantation Elevated Storage Tank Improvements - The final completion date per the contract was March 26, 2025. The tank has passed final disinfection and is currently online. eHT issued a punch list to Phoenix with items that remain outstanding for final completion and acceptance. Phoenix has been working towards getting the tank online. Liquidated damages are still continuing. • Acton Loop Water Line Extension Improveme.ots ....._ eHT and Staffm_e_t _onsite with landowners who requested a change to the easement on the shopping center site to include modifications to the existing sewer service line from one of the buildings. The easement has been modified, eHT is adjusting plans and project manual to reflect changes. Once plans are adjusted, eHT will submit 3 - - for TxDOT utility permits and coordinate with Staff for County approval to move forward with advertising the project. • Fall Creek Hwy. Water Line Improvements- eHT is finalizing design survey data to locate existing utilities and working on plans and specifications for review with Staff. Subsurface Utility Engineering (SUE)