The Operational Report was presented by T J Riggio. He updated the Board on the
Staff Report & Agenda Item Details
The Operational Report was presented by T J Riggio. He updated the Board on the following: Rehab at Lift Station No. 11 in DCBE - The mechanical repairs are complete; coordinating with Grimsley, the low bidder at $42,730 for the electrical improvements. Grimsley is waiting for the availability of our trailer pump since the lift station will need to be down for several hours to complete their work; the trailer pump is currently being used at LS 06 in PP. LS 06PP - Lost both pumps and have no backup, it is a single phase lift station which was overlooked when the pumps were inventoried. Landings East Lift Station - The lift station is tripping, it spikes at 100 amps on start up and then drops to 18 amps. The developer is looking into this to determine the issue. AMUD has not yet accepted the lift station.