H • REGULARActon Municipal Utility District (Hood County)

The Engineer's Report was presented by Chris Hay, P.E. of eHT. He reported on the

Presented in: Board of Directors Regular Meeting - May 20, 2026 on 2026-05-20
Meeting Agenda PDF

Staff Report & Agenda Item Details

The Engineer's Report was presented by Chris Hay, P.E. of eHT. He reported on the following: • WWTP #2 Improvements - The current substantial and final completion dates are June 5, 2025 and July I 0, 2025 respectively based on the approval of Change Order 2. The new sludge pumps are in and wired, working with BAR on installation. The new sludge pumps will allow operation and startup of the dewatering system which should put completion of the project in June and then follow up with a walk through inspection. • Pecan Plantation Elevated Storage Tank Improvements - The final completion date per the contract was March 26, 2025. The contractor, Phoenix Fabricators and Erectors, LLC (Phoenix), reached final completion on April 7, 2026, the tank is in service and all punch list items are complete. Phoenix has disputed the validity of liquidated damages in relation to their delay in completing the project. Coordination is ongoing regarding final payment and close-out of the project. • Acton Loop Water Line Extension Improvements- eHT and Staff met onsite with landowners who requested a change to the easement on the shopping center site to include modifications to the existing sewer service line from one of the buildings. Plans were reviewed with Staff on April 16th, and eHT is wrapping up revisions from that review meeting to finalize plans for right of way permits, which should be submitted this month. • Fall Creek Highway Water Line Improvements-The design