4. WWTP Improvements Project – We are in design of the wastewater treatment plant improvements project. Working toward 30% completion next week. Project Authorization: 2/25/2025 Estimated Construction Cost: $539,000 Scheduled Design Completion: 7/6/2025 FB 131 Construction Cost: $311,200 Scheduled Bid & Contract Date: 9/23/2025 Engineering Cost: $133,600 Scheduled Construction NTP: 10/28/2025 FB 131 Engineering Cost: $77,150 Scheduled Substantial Completion: 5/2/2026 Project Expenses: $2,500
Bastiat Liberty & Property Rights Analysis
This motion is scored as RESTRAINS_GOVERNMENT (Impact Weight: 2.7/10). Under the Bastiat Liberty Watchdog Index, voting YES on measures that cap or reduce ad valorem tax burdens, expand taxpayer exemptions, retire debt early, enforce competitive bidding caps, or remove regulatory/zoning barriers to private property rights earns a positive Pro-Liberty score.