The Operational Report was presented by T J Riggio. He updated the Board on the
Presented in: Board of Directors Regular Meeting - October 15, 2025 on 2025-10-15
Staff Report & Agenda Item Details
The Operational Report was presented by T J Riggio. He updated the Board on the rehab for Lift Station No. 11 in DCBE. He received three quotes for the electrical panel; the low bid was Grimsley at $42,730. AMUD crews will do repairs for the plumbing and structural work in the current wet well, the cost is bid at $26,078. The electrical upgrades will be a part of the eventual project rebuild. The plumbing and 3 structural work will not carry over to the new rebuilt lift station but is needed at this time in order to have an operable lift station.