Back to Docket Search
Total Estimated Contract Price 845,000.00 as of this Report B. Actual Cost as of this Report 838,900.00 C. Total Previously Paid to Contractor 717,979.50 D. Amount Retained at: 10% 83,890.00 E. Estimated Cost Remaining 6,100.00 F. Percent Construction Com
Presented in: Sienna Plantation MUD #1 Board Meeting - 2025-03-27 on 2025-03-27
Official Roll-Call Vote
Routine / Procedural • 0.0 Score Impact
PASSED (5 - 0)
“Motion to approve Total Estimated Contract Price 845,000.00 as of this Report B. Actual Cost as of this Report 838,900.00 C. Total Previously Paid to Contractor 717,979.50 D. Amount Retained at: 10% 83,890.00 E. Estimated Cost Remaining 6,100.00 F. Percent Construction Com”
CB
Carl Bowles
Director, Place 1 (Place 1)
YES
JC
James Condrey
Director, Place 2 (Place 2)
YES
KD
Kelly D. Shipley
Director, Place 3 (Place 3)
YES
JF
James Feuerbach
Director, Place 4 (Place 4)
YES
RB
Robbie Bates
Director, Place 5 (Place 5)
YES
Staff Report & Agenda Item Details
Total Estimated Contract Price 845,000.00 as of this Report B. Actual Cost as of this Report 838,900.00 C. Total Previously Paid to Contractor 717,979.50 D. Amount Retained at: 10% 83,890.00 E. Estimated Cost Remaining 6,100.00 F. Percent Construction Complete
Bastiat Liberty & Property Rights Analysis
This docket item is classified as NEUTRAL (0.0 Score Impact). Routine administrative reports, monthly accounts payable/disbursement registers, minutes approvals, and procedural motions are logged for public transparency but carry zero weight in calculating an official's Roll-Call Freedom Score.