19 • FINANCESienna Plantation Municipal Utility District #4 (Fort Bend County)

She reviewed and recommended approval of Pay Estimate No. 3 in the amount of$ 439,082.82, payable to R Construction. Ms. Carriage requested the Board approve an offsite waterline easement to serve Sienna Section 45B. Ms. Carriage updated the Board on road

Presented in: Sienna Plantation MUD #4 Board Meeting - 2022-04-04 on 2022-04-04
Meeting Agenda PDF

Official Roll-Call Vote

Restrains Gov't • 4.7/10 Impact Weight
PASSED (5 - 0)
“Motion to approve She reviewed and recommended approval of Pay Estimate No. 3 in the amount of$ 439,082.82, payable to R Construction. Ms. Carriage requested the Board approve an offsite waterline easement to serve Sienna Section 45B. Ms. Carriage updated the Board on road”
MR
Maris Reynolds
Director, Place 1 (Place 1)
YES
RS
Ray Sick
Director, Place 2 (Place 2)
YES
JM
Jose Munoz
Director, Place 3 (Place 3)
YES
RV
Robert Vacek
Director, Place 4 (Place 4)
YES
BI
Bryan Ives
Director, Place 5 (Place 5)
YES

Staff Report & Agenda Item Details

She reviewed and recommended approval of Pay Estimate No. 3 in the amount of$ 439,082.82, payable to R Construction. Ms. Carriage requested the Board approve an offsite waterline easement to serve Sienna Section 45B. Ms. Carriage updated the Board on road repairs for Sienna Section 12 Phase II. She stated that bids were received for road repairs for Sienna Section 12 Phase II. Ms. Carriage recommended that the Board award the contract to Infrastructure Construction Services (" Infrastructure Construction") in the amount of$ 173,433. 75. The Board concurred that, in its judgment, Infrastructure Construction was a responsible bidder who would be most advantageous to the District and would result in the best and most economical completion of the project. Ms. Carriage updated the Board on road repairs for Sienna Section 20 Phase II. e stated that bids were received for road repairs for Sienna Section 20 Phase II. Ms. Carriage recommended that the Board award the contract to Infrastructure Construction in the amount of $ 67,942. 75. The Board concurred that, in its judgment, Ififrastructure Construction was a responsible bidder who would be most advantageous to the District and would result in the best and most economical completion of the roject. Ms. Stephens stated that the Board has surplus road bond proceeds which may e used for Sienna Section 12, Phase II and Sienna Section 20 Phase II. After review and discussion, and based on the engineer' s recommendation, Director Vacek moved to ( 1) approve the engineer' s report; ( 2) approve the Pay Estimates, as presented, and accept the completed projects; ( 3) accept the easement; ( 4) award the construction contracts, as recommended, based upon the District engineer' s recommendation and subject to approval of the payment and performance bonds and review of the certificates of insurance and endorsements, if any, provided by the gontractors; and ( 5) authorize LJA to use the surplus road bond proceeds for road 3- 8W

Bastiat Liberty & Property Rights Analysis

This motion is scored as RESTRAINS_GOVERNMENT (Impact Weight: 4.7/10). Under the Bastiat Liberty Watchdog Index, voting YES on measures that cap or reduce ad valorem tax burdens, expand taxpayer exemptions, retire debt early, enforce competitive bidding caps, or remove regulatory/zoning barriers to private property rights earns a positive Pro-Liberty score.