1 • OPERATIONSSienna Plantation Municipal Utility District #1 (Fort Bend County)

Maintenance & Repairs:  Wastewater Treatment Plant i. I. Replaced the poly line from HPT to controls due to a leak. Tested and put back online. ($1,149.50) ii. Lost power to the plant, but the generator would not run. Found fuse blown on the pole and con

Presented in: Sienna Plantation MUD #1 Board Meeting - 2026-01-22 on 2026-01-22
Meeting Agenda PDF

Official Roll-Call Vote

Routine / Procedural • 0.0 Score Impact
PASSED (5 - 0)
“Motion to approve Maintenance & Repairs:  Wastewater Treatment Plant i. I. Replaced the poly line from HPT to controls due to a leak. Tested and put back online. ($1,149.50) ii. Lost power to the plant, but the generator would not run. Found fuse blown on the pole and con”
CB
Carl Bowles
Director, Place 1 (Place 1)
YES
JC
James Condrey
Director, Place 2 (Place 2)
YES
KD
Kelly D. Shipley
Director, Place 3 (Place 3)
YES
JF
James Feuerbach
Director, Place 4 (Place 4)
YES
RB
Robbie Bates
Director, Place 5 (Place 5)
YES

Staff Report & Agenda Item Details

Maintenance & Repairs:  Wastewater Treatment Plant i. I. Replaced the poly line from HPT to controls due to a leak. Tested and put back online. ($1,149.50) ii. Lost power to the plant, but the generator would not run. Found fuse blown on the pole and contacted Center Point. Cut the main breaker and started the generator to the power plant. Waited for repairs to be completed and transferred back to line power. ($1,435.50) iii. Found blower on odor control had failed. The motor was tested and had shorted out. Reached out to the contractor for warranty. Motor replaced by contractor. ($660.00) iv. Vactor cleaned out the wet well of grease and debris. ($1,714.42) v. Blower manufacturer provided PM on blowers. ($9,976.86)  Lift Station i. Trammel Fresno L12- Replaced VFD for LP#2 that failed. ($3,303.32) ii. Sienna Parkway L2, Sienna Springs L11, Trammel Fresno L12, Brushy Lake L14, Steep Bank L9, Scanlan Trace L6, Scanlan Trace L5, Waters Lake L7, Steep Bank L9- Vactor cleaned out wet well of grease and debris. ($19,586.83) iii. Waters Lake L7- Pulled pumps and removed debris. ($607.21) iv. Waters Lake L7- Filled up bypass pumps on multiple occasions. ($2,611.88) v. Trammel Fresno L12- Found pump #2 was not running. Tested and found the pump shorted out. Took to the shop for repairs. ($2,090.00)  Water Distribution i. Performed preventive maintenance on the entire disinfection system at all three water plants. ($3,349.95) ii. Murray Ct- Purchased and replaced the bad coupling on booster pump #1. ($787.92) iii. McKeever Rd and Murray Ct- Used compressor to air up HPT tanks. ($1,482.49)

Bastiat Liberty & Property Rights Analysis

This docket item is classified as NEUTRAL (0.0 Score Impact). Routine administrative reports, monthly accounts payable/disbursement registers, minutes approvals, and procedural motions are logged for public transparency but carry zero weight in calculating an official's Roll-Call Freedom Score.