Ord. 2026-26.City of Laredo (Webb County)

Consideration to award a construction contract to the lowest responsible, responsive bidder Soliz Paving, Inc, Laredo, Texas in the amount not to exceed $3,911,966.60 for FY26-ENG-52 Springfield Avenues Extension, Phase 1 Project for the total base bid. Construction contract time is 220 working days. Funding is available in the 2024A Certificate of Obligation Bond. 1. Soliz Paving Inc, Laredo, Texas Total Base Bid: $3,911,966.60 2. SAL Construction Management LLC, Laredo, Texas Total

Bastiat Overreach Score: 60/100
Passed: 2026-10-05 • Effective: 2026-10-05

Executive Summary & Impact

Consideration to award a construction contract to the lowest responsible, responsive bidder Soliz Paving, Inc, Laredo, Texas in the amount not to exceed $3,911,966.60 for FY26-ENG-52 Springfield Avenues Extension, Phase 1 Project for the total base bid. Construction contract time is 220 working days. Funding is available in the 2024A Certificate of Obligation Bond. 1. Soliz Paving Inc, Laredo, Texas Total Base Bid: $3,911,966.60 2. SAL Construction Management LLC, Laredo, Texas Total Base Bid: $4,729,752.10 3. Mage 4 Group, Ltd., Laredo, Texas Total Base Bid: $5,471,907.00 4. 360 General Contractor Inc., Laredo, Texas Total Base Bid: $7,764,638.95 Refer to attached letter of recommendation from Porras Nance Engineering Company, Laredo, Texas.

View Official Municipal Publication

Legislative Enactment & Roll-Call History

26. • City of Laredo City Council2026-10-05
Consideration to award a construction contract to the lowest responsible, responsive bidder Soliz Paving, Inc, Laredo, Texas in the amount not to exceed $3,911,966.60 for FY26-ENG-52 Springfield Avenues Extension, Phase 1 Project for the total base bid. Construction contract time is 220 working days. Funding is available in the 2024A Certificate of Obligation Bond. 1. Soliz Paving Inc, Laredo, Texas Total Base Bid: $3,911,966.60 2. SAL Construction Management LLC, Laredo, Texas Total
Outcome: PASSED (9-0) • Motion to approve Consideration to award a construction contract to the lowest responsible, responsive bidder Soliz Paving, Inc, Laredo, Texas in the amount not to exceed $3,911,966.60 for FY26-ENG-52 Springfield Avenues Extension, Phase 1 Project for the total base bid. Construction contract time is 220 working days. Funding is available in the 2024A Certificate of Obligation Bond. 1. Soliz Paving Inc, Laredo, Texas Total Base Bid: $3,911,966.60 2. SAL Construction Management LLC, Laredo, Texas Total

Official Legal Text & Codified Sections

OFFICIAL LEGISLATIVE RECORD — CITY OF LAREDO
Instrument / Docket Number: Ord. 2026-26. (Agenda Item 26.)
Meeting: City of Laredo City Council
Date Enacted: 2026-10-05
Roll-Call Outcome: PASSED (9 YES - 0 NO)
Category: Municipal Ordinance

VERBATIM DOCKET TEXT & SUMMARY:
Consideration to award a construction contract to the lowest responsible, responsive bidder Soliz Paving, Inc, Laredo, Texas in the amount not to exceed $3,911,966.60 for FY26-ENG-52 Springfield Avenues Extension, Phase 1 Project for the total base bid. Construction contract time is 220 working days. Funding is available in the 2024A Certificate of Obligation Bond.

1. Soliz Paving Inc, Laredo, Texas
   Total Base Bid: $3,911,966.60
2. SAL Construction Management LLC, Laredo, Texas
   Total Base Bid: $4,729,752.10
3. Mage 4 Group, Ltd., Laredo, Texas
   Total Base Bid: $5,471,907.00
4. 360 General Contractor Inc., Laredo, Texas
   Total Base Bid: $7,764,638.95

Refer to attached letter of recommendation from Porras Nance Engineering Company, Laredo, Texas.