Consider for approval Change Order #1 to the contract with Intermountain Slurry Seal, Inc. for the FY2025 Pavement Preservation project (RFP #25-16) decreasing the contract by $106,552.04 from the amount of $1,496,302.39 to the final amount of $1,389,750.35; Authorizing the City Manager to execute all necessary documents upon final approval by the City Attorney. (R Winiecke)
Bastiat Overreach Score: 54/100
Passed: 2026-09-17 • Effective: 2026-09-17
Executive Summary & Impact
Consider for approval Change Order #1 to the contract with Intermountain Slurry Seal, Inc. for the FY2025 Pavement Preservation project (RFP #25-16) decreasing the contract by $106,552.04 from the amount of $1,496,302.39 to the final amount of $1,389,750.35; Authorizing the City Manager to execute all necessary documents upon final approval by the City Attorney. (R Winiecke)
Legislative Enactment & Roll-Call History
O. • City of Galveston City Council Regular Meeting2026-09-17
Consider for approval Change Order #1 to the contract with Intermountain Slurry Seal, Inc. for the FY2025 Pavement Preservation project (RFP #25-16) decreasing the contract by $106,552.04 from the amount of $1,496,302.39 to the final amount of $1,389,750.35; Authorizing the City Manager to execute all necessary documents upon final approval by the City Attorney. (R Winiecke)Outcome: PASSED (7-0) • Motion to approve Consider for approval Change Order #1 to the contract with Intermountain Slurry Seal, Inc. for the FY2025 Pavement Preservation project (RFP #25-16) decreasing the contract by $106,552.04 from the amount of $1,496,302.39 to the final amount of $1,389,750.35; Authorizing the City Manager to execute all necessary documents upon final approval by the City Attorney. (R Winiecke)
Official Legal Text & Codified Sections
OFFICIAL LEGISLATIVE DOCKET RECORD — CITY OF GALVESTON Instrument / Docket Number: Ord. 2026-09-17-O. (fbefa6) (Agenda Item O.) Meeting: City of Galveston City Council Regular Meeting Date Enacted: 2026-09-17 Roll-Call Outcome: PASSED (7 YES - 0 NO) Category: General Regulation Source Document: https://galvestontx.civicclerk.com/Web/Gen/MeetingDetails?meetingId=8208 VERBATIM DOCKET TEXT & SUMMARY: Consider for approval Change Order #1 to the contract with Intermountain Slurry Seal, Inc. for the FY2025 Pavement Preservation project (RFP #25-16) decreasing the contract by $106,552.04 from the amount of $1,496,302.39 to the final amount of $1,389,750.35; Authorizing the City Manager to execute all necessary documents upon final approval by the City Attorney. (R Winiecke)