Consideration to reject all bids received for FY24-ENG-89 Animal Care Services - New Veterinary Hospital and Master Planning Project, and authorization to rebid the project, as the bids received exceed the estimated budgeted amount. There is no financial impact at this time. 1. Cobalt Construction, Laredo, Texas Total base bid: $2,293,490.01 2. Zertuche Construction Texas, LLC, Laredo, Te
Executive Summary & Impact
Consideration to reject all bids received for FY24-ENG-89 Animal Care Services - New Veterinary Hospital and Master Planning Project, and authorization to rebid the project, as the bids received exceed the estimated budgeted amount. There is no financial impact at this time. 1. Cobalt Construction, Laredo, Texas Total base bid: $2,293,490.01 2. Zertuche Construction Texas, LLC, Laredo, Texas Total base bid: $2,410,333.00 3. Mage 4 Group, Ltd., Laredo, Texas Total base bid: $2,473,775.00 4. STBP, Inc., Corpus Christi, Texas Total base bid: $2,651,730.34 5. Sima Contractors, LLC, Laredo, Texas Total base bid: $2,719,270.00 6. Quantcorp Construction, LLC, Laredo, Texas Total base bid: $2,749,800.00 7. ABBA Construction, LLC, Laredo, Texas Total base bid: $3,432,646.55 Refer to attached letter of recommendation from XA Collective LLC, San Antonio, Texas.
Legislative Enactment & Roll-Call History
Official Legal Text & Codified Sections
OFFICIAL LEGISLATIVE RECORD — CITY OF LAREDO
Instrument / Docket Number: Ord. 2026-25. (Agenda Item 25.)
Meeting: City of Laredo City Council Meeting
Date Enacted: 2026-10-05
Roll-Call Outcome: PASSED (9 YES - 0 NO)
Category: Municipal Ordinance
VERBATIM DOCKET TEXT & SUMMARY:
Consideration to reject all bids received for FY24-ENG-89 Animal Care Services - New Veterinary Hospital and Master Planning Project, and authorization to rebid the project, as the bids received exceed the estimated budgeted amount. There is no financial impact at this time.
1. Cobalt Construction, Laredo, Texas
Total base bid: $2,293,490.01
2. Zertuche Construction Texas, LLC, Laredo, Texas
Total base bid: $2,410,333.00
3. Mage 4 Group, Ltd., Laredo, Texas
Total base bid: $2,473,775.00
4. STBP, Inc., Corpus Christi, Texas
Total base bid: $2,651,730.34
5. Sima Contractors, LLC, Laredo, Texas
Total base bid: $2,719,270.00
6. Quantcorp Construction, LLC, Laredo, Texas
Total base bid: $2,749,800.00
7. ABBA Construction, LLC, Laredo, Texas
Total base bid: $3,432,646.55
Refer to attached letter of recommendation from XA Collective LLC, San Antonio, Texas.