Discussion and possible action to approve the use of the contingency allowance as stipulated under §4.3 (allowances) under the construction agreement between Webb County and Mor-Wil, LLC in an amount not to exceed $79,121.00 for Material Testing and the installation and removal of an Air Bridge for ARPA Project No. 0004, 0005, 0009, 0010, 0012 and 0013 – Waterline Projects and to further authorize
Official Roll-Call Vote
Staff Report & Agenda Item Details
Discussion and possible action to approve the use of the contingency allowance as stipulated under §4.3 (allowances) under the construction agreement between Webb County and Mor-Wil, LLC in an amount not to exceed $79,121.00 for Material Testing and the installation and removal of an Air Bridge for ARPA Project No. 0004, 0005, 0009, 0010, 0012 and 0013 – Waterline Projects and to further authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [Account #2703-5205-001-474502-103 (W/Line Exten RioBravo Man Hein Rd), Account #2703-5205-001-474502-104 (Main w/line Exten South Fire St), Account #2703-5205-001-474502-105 (Dist W/line La Presa Comm Center), Account #2703-5205-001-474502-106 (Dist W/line ManHeinRd South Fire Sta), Account #2703-5205-001-474502-107 (Connect w/line Water Dispenser), Account #2703-5205-001-474502-108 (Distribu w/lines Col LaPresa)] Issue: Based on the request from Ardurra Group, Inc., Engineer (Ronald W. Miller II) a revision was requested to alter the testing intervals from every 150-LF to every 500-LF for the proposed water line at a cost of $43,371.00 and the installation and removal of a temporary Air Bridge (4' x 8" x 16') is required by Enterprise Gas in order to protect the existing gas line during the duration of the water line project at a cost of $35,750.00. Solution: Consideration to authorize the use of $79,121.00 from the owner's contingency allowance funds. Result: If approved, the contractor will be authorized to use the owner's contingency amount as approved by Commissioners Court. There will be no increase or decrease to the original contract sum.
Bastiat Liberty & Property Rights Analysis
This motion is scored as EXPANDS_GOVERNMENT (Impact Weight: 4.9/10). Under the Bastiat Liberty Watchdog Index, measures that increase tax rates or fee schedules, issue new debt or Certificates of Obligation, expand regulatory/zoning restrictions on private land use, or authorize unbudgeted spending expansions reduce an official's Freedom Score when voted YES (and reward dissenting NO votes).